Traffic Advisory: Beginning at 7a.m. on July 26th the turn lane from eastbound Drennan Road merging onto southbound Academy will be closed .Click here to view the complete Advisory.

Milton E. Proby Weekly Construction Update
Anticipated Construction Activities for September 3, 2010- September 10, 2010
- Ames Construction Inc. will observe the Labor Day Holiday, Monday, September 6, 2010. No Work will occur during this time.
- Soundwall installation is complete, staining of the panels has begun.
- Construction of the FMIC siphon box has begun. This system will allow irrigation water to continue uninterupted after the relocation of Academy Boulevard.
- Construction of Pier 3 for the Ramp C Bridge will begin next Wednesday and continue Thursday and Friday.
- Fill for soffit to construct the east end of Ramp C Bridge between piers 5 and 6 and abutment 7 will continue.
- Sub-grade finish work will continue on Proby, at the east end of Hancock.
- Form work and the pouring of piers 2, 4, 5 & 6 for the Ramp C Bridge is now complete.
- The sidewalk at the southwest corner of Drennan and Academy remains closed until further notice.
- Sidewalk access in the area of the old north sound wall remains closed.
- Storm-drainage work continues.
- We are continuing to pour concrete on drainage structures.
- Utility relocations are ongoing.
|