Traffic Advisory: Beginning at 7a.m. on July 26th the turn lane from eastbound Drennan Road merging onto southbound Academy will be closed .Click here to view the complete Advisory.

All scheduled dates are subject to change based on unexpected weather occurrences.
30-Day Outlook | July-August 2010
Academy Boulevard Work
• Temporary traffic realignments to facilitate work in the area
• Construct the first phase of the Founders Mutual Irrigation Channel (FMIC)
• Begin substructure construction for the Ramp C Bridge over Academy
• Continue mass earthwork on Proby Parkway between Academy and Hancock
• Relocate fiber and power on Academy
Hancock to Powers Work
• Install pipe, box culvert and drainage structures
• Begin Construction of the soundwalls from Hancock to Powers on the north and south side of the existing Proby Parkway
• Mass earthwork and completion of the new Proby Parkway westbound lanes
Project Milestones
June 7, 2010 through October 2010
• Close Proby Parkway from Hancock to Powers
October 2010
• Re-open Proby Parkway between Hancock Expressway and Powers Boulevard
September 2010
• Completion of Soundwalls on the north and south side of the existing Proby Parkway
August 2011
• Open Proby Parkway (Except Ramps D & E)
October 2011
• Open Proby Parkway (All Ramps)